Delegations
- Delegations
- What is the General State Administration in the Territory?
- Legislation
- Delegations in Autonomous Communities
- Government Delegation in the Autonomous Community of Andalusia
- Government Delegate
- News
- Proyectos, Campañas e Información
- Servicios y Directorio
- Government Sub-delegation in Seville
- Government Sub-delegation in Almeria
- Government Sub-delegation in Cadiz
- Government Sub-delegation in Cordoba
- Government Sub-delegation in Huelva
- Government Sub-delegation in Jaen
- Government Sub-delegation in Malaga
- Government Sub-delegation in Granada
CU-PEol-176 GECAMA EÓLICO
RESOLUCIONES
Autorización Administrativa de Explotación (AAE) - 14/10/2022
CORRESPONDIENTES AL PROYECTO DEL PARQUE EÓLICO (PEOL-176) GECAMA EÓLICO DE 329,2 MW, LAS SUBESTACIONES 33/132 KV Y 132/400 KV, LAS LÍNEAS SUBTERRÁNEAS A 33 KV Y 132 KV Y LA LÍNEA DE ENERGÍA ELÉCTRICA A 400 KV PARA EVACUACIÓN, UBICADO EN LA PROVINCIA DE CUENCA.
Autorización Administrativa de Construcción (AAC) - 04/06/2020
Declaración de Utilidad Pública (DUP) - 5/03/2020 - BOE-A-2020-4060
Autorización Administrativa - 17/01/2018 - BOE-A-2018-1720
Declaración de Impacto Ambiental (DIA) - 30/03/2017 - BOE-A-2017-4098